Shelton Canada Corp. has provided an operational update on
its projects in Ukraine - Kashtan Petroleum Joint Venture -- Lelyaki Oil Field
Well No.307 has been
cased for production and well completion procedure has been completed. The well
was drilled to a total depth of 1,960 metres and encountered measured depth oil
saturated porous zones of 5.0 metres in the lowermost K zone and 8.6 metres in
the dolomite reservoir of the P1+P2 zone. The well has been completed in the K
zone and initial well productivity after cleanup is approximately 38 metric
tonnes of fluid per day with oil cut ranging from 96% to 97.5% (average gross
284 barrels of oil per day and net
Lease construction is nearing completion for the next well No.304
A, with planned spud date early in 2009. This well will be followed later in
2009 with the drilling of well No.308.
This work is an ongoing part of the Kashtan Petroleum Joint
Ventures plan to fully exploit the remaining oil reserves in the Lelyaki field
through optimal placement of infill production wells. In addition, the Joint
Venture anticipates re-entering and side-track drilling of four other suspended
wells in different parts of the field during 2009. These well interventions
show very good economics as the capital cost is much lower than new drilling.